Customer

SIA “HoSt Energo”

Fuel

Biofuel

Power

9 MW

Project

Construction of a combined heat and power plant in the city of Kraslava in the Republic of Latvia

Installed

2008

Description

Renovation and extension construction of the combined heat and power plant in the city of Kraslava in the Republic of Latvia with the installation of a new biofuel-powered superheated steam boiler set Q=9 MW.

Why are we a good partner?

We can offer our partners and customers top expertise in the field, high-quality delivery, installation, and after-sales service.

The oldest device set up and working by us is already more than 25 years old. We estimate the lifetime of our newer boiler houses to be 20+ years, and the total maintenance cost is 10-20% of the purchase price.

Our factory constantly tests new ways to make products more efficient. Everything that leaves our factory always meets the regulations and requirements.