Rolfs Såg 8 MW Boiler Plant Technology – Manufacturing and Installation
Description
Tamult manufactured and installed most of the technological equipment for the 8 MW Rolfs Såg biomass boiler plant in Kalix, Sweden.
The scope of work included furnace manufacturing, fuel handling and ash removal systems, process piping, steel structures and flue gas cleaning equipment.
Customer | Saxwerk AB |
Fuel | Woodchips |
Power | 8 MW |
Project | Rolfs Såg Biomass Boiler Plant Construction |
Installed | 2026 |
Country | Sweden |
Why are we a good partner?
We can offer our partners and customers top expertise in the field, high-quality delivery, installation, and after-sales service.
The oldest device set up and working by us is already more than 25 years old. We estimate the lifetime of our newer boiler houses to be 20+ years, and the total maintenance cost is 10-20% of the purchase price.
Our factory constantly tests new ways to make products more efficient. Everything that leaves our factory always meets the regulations and requirements.