Ülenurme small town boiler house 2MW

ash_container_10m3
biomass boiler house
biokütuse mehhaniseeritud ladu
boiler house automation
Tõrvandi biomass boiler house with capacity of 2MW
biomass screw

Description

Within the framework of this project, a turnkey biofuel boiler house with moving grates was installed, with a fuel loading of 200m3/h and storage for moving grates of 500m3. Tamulti specialists also installed the flue gas system, piping, automation, and the building.

Customer

SW Energia OÜ

Fuel

Wood chips and peat with a humidity of 15-45%

Power

2 MW

Project

Ülenurme small town boiler house with a capacity of 2MW

Installed

2019

Why are we a good partner?

We can offer our partners and customers top expertise in the field, high-quality delivery, installation, and after-sales service.

The oldest device set up and working by us is already more than 25 years old. We estimate the lifetime of our newer boiler houses to be 20+ years, and the total maintenance cost is 10-20% of the purchase price.

Our factory constantly tests new ways to make products more efficient. Everything that leaves our factory always meets the regulations and requirements.